If a battery has a nominated capacity of 205 kWh and a usable battery capacity of 195 kWh, should it be considered under BESS4 or BESS5?
A battery with a usable battery capacity of 195 kWh (as defined in the PDRS Rule) would be eligible under BESS4 because the usable battery capacity is less than or equal to 200 kWh.
For BESS5, the usable battery capacity must be above 200 kWh.