Adding a Battery & BSTC Compliance in Bridge Select

Watch the video or follow this step-by-step guide to enter battery storage specifications, configure Battery Small-scale Technology Certificates (BSTCs), and review installer presence verification in Bridge Select.

Step 1: Set Grid Connection & Add Battery

  1. Navigate to the 2. System Details tab.
  2. Under the Connection & Battery Details (if applicable) section, select your Connection Type of Electricity Grid (e.g. Connected to an electricity grid).
  3. Click the blue + Add Battery button to open the equipment entry fields.

 

Step 2: Configure Battery Specifications & Modules

  1. Select the Battery manufacturer from the dropdown list (e.g. Sungrow Power Supply Co Ltd).
  2. Choose the specific Battery model and Battery series.
  3. Enter the Number of batteries and Number of modules.

    Important: The number of modules and the number of batteries must match (for example, if there are four modules, enter four batteries).

  4. Click + Add to attach the battery unit to the job record.

 

Step 3: Set Installation Location & Enable BSTC

  1. Under Location where battery will be or is installed?, select either Indoor or Outdoor.
  2. Tick the BSTC checkbox to activate battery certificates on the job.
  3. Complete the required battery questionnaire:
    • Confirm if there is a room behind the mounting wall.
    • Confirm whether the system is configured to provide backup power.
    • Enter the Financial payment amount (the out-of-pocket cost paid by the customer, which must reconcile with the invoice).
    • Answer the compliance questions regarding default manufacturer settings, Virtual Power Plant (VPP) capability, and retailer involvement.
  4. Confirm whether the battery is connecting to a new inverter and check the system warranty duration.

 

Step 4: Verify Installer Presence Selfies

  1. Navigate to the 3. Install Details tab.
  2. Review the Installer Presence panel to monitor the verification photos uploaded by the technician via the mobile app.
Note: there are six required on-site selfies are captured across the job milestones:
Solar PV Selfies: Start, Middle, and End
Battery Selfies: Start, Middle, and End

 


Step 5: Save and Exit

  1. Once all details, documentation, and declarations are complete, click Check Information & Save to validate the submission.
  2. If you need to pause and return to the job later, click Partial Save & Exit at the bottom of the screen to retain your entered data.

Note: Installers must capture presence selfies at the required intervals in real-time through the mobile app, as the Clean Energy Regulator (CER) requires timestamped evidence for battery certificate approvals.